Floor Systems

Scope: 

106 x 6 car train sets for 95TS (Northern line) – 636 cars

Project commenced Q1:2013 with completion during Q2:2015

63 x 7 car train sets for 95TS (Northern line) – 441 cars

Project commenced Q4:2016 with completion during Q1:2019

 

Designed by PLP in-house engineering team

Cab area flooring added to the scope i.e. as well as the saloon areas

Modular system designed to permit individual panel lift in the event of needing to access piping, electrics etc. situated under the floor thus providing a significant time (and material cost) saving for such maintenance activities

Technically compliant to applicable LUL standards and specifications

Materials sourced by PLP

End product manufactured by PLP

Assisting with first vehicle fit on-site at TfL depots

Other products being supplied as part of the contract include wheelchair area partitions, internal and external sill plates and all applicable tooling